How the quantities are computed
Each measured item is one row; the Material picks the conversion. Bulk materials (mulch, topsoil, compost, stone) use the standard coverage formula — area times depth, divided by 324 — to get cubic yards, then a waste allowance and an optional bag count:
cu yd = area (sq ft) × depth (in) ÷ 324 ← 324 = 12 × 27
cu yd w/ waste = cu yd × (1 + waste% ÷ 100)
bags = ceil(cu yd w/ waste × bags-per-cu-yd) ← 13.5 (2 cu ft) / 9 (3 cu ft)
sod pallets = ceil(area × (1 + waste% ÷ 100) ÷ pallet coverage) ← default 500 sq ft
sod rolls = ceil(area × (1 + waste% ÷ 100) ÷ 10) ← a roll = 10 sq ft
paver base = area × base depth ÷ 324 ← base depth 5 in (4–6 in)
bedding sand = area × 1 ÷ 324 ← 1 in bedding
plants = count (pass-through, "each")
edging = round(length × (1 + waste% ÷ 100)) ← lin ft A 500 sq ft bed at 3 in is 4.63 cu yd ≈ 63 two-cubic-foot bags; a 5,000 sq ft sod area is 10 pallets at 500 sq ft each; an 800 sq ft paver patio needs about 12.35 cu yd of base aggregate plus 2.47 cu yd of bedding sand. Discrete order units (bags, pallets, rolls) round up — you cannot buy a fraction of a bag.
Coverage rates are standard estimates, not guarantees. Sod pallets vary by grower and by how the sod is cut (450 / 500 / 600 sq ft is typical; 400–700 across slab, mini-roll, and large-roll pallets) and stone is often sold by the ton with a density that varies by type — confirm coverage, depth, and waste with your supplier before ordering. This sheet is quantity-only and never prices anything; there is no cost, labor, or markup field. It is not an inventory ledger — it is a per-job order list computed from the measurements you enter.
A landscape material takeoff is the step between measuring and buying: it turns the areas, lengths, and counts you pulled off the site or the plan — bed square footage, lawn area, patio footprint, edging runs, plant counts — into a quantity bill you can hand to a supplier. Cubic yards of mulch, pallets of sod, tons of stone, cubic yards of paver base, plants by the each, edging by the linear foot. No prices, no labor, no totals. Just how much to buy, so you order once and neither run short nor pay to haul back a surplus.
This is a free, no-signup Excel workbook, plus the preview above that computes one row so you can watch the conversion before you download anything.
Takeoff or estimate? Two different documents
This sheet is deliberately quantity-only. There are no unit prices, no labor hours, no markup, and no dollar totals anywhere on it — that is the point. The takeoff is the how much to buy step that comes before pricing, and keeping it clean is what lets you hand the summary to a yard without it reading like a quote.
When you are ready to attach cost, take these quantities to the landscaping estimate calculator. When the number turns into an offer the client signs, the landscaping estimate & bid template is the priced document — phase-grouped lines, markup, overhead, tax, signature. Three documents, three jobs: measure, then quantify, then price. Collapse the middle one into the last and you stop being able to tell a short order from a thin margin — the yard hands you eight yards of mulch when the beds needed eleven, and the shortfall shows up as a cost overrun instead of a counting error.
It is also not an inventory system. This is a per-job shopping and haul list computed from the measurements in front of you, not a running stock ledger.
What is on the takeoff sheet
Each row is one measured item: zone or phase · material · measured value · unit · depth · waste % · notes, and the sheet returns an order quantity and the order unit you will actually buy in. The bottom rolls everything up into a consolidated order summary — one line per material, quantity only — which prints portrait as a clean truck copy to carry into the yard.
The download has two visible tabs: a blank takeoff sheet and a sample-filled one carrying a complete worked job you overwrite. A hidden Conversions tab holds the coverage constants the formulas read. Everything is local cell formulas, so it opens in Excel, Google Sheets, or LibreOffice with no macros and nothing to enable.
How the quantities are computed
Bulk materials use the standard coverage method: area × depth ÷ 324, where the 324 is 12 inches per foot times 27 cubic feet per cubic yard. Easy Takeoffs runs the same worked example for landscape takeoffs — a 500 sq ft bed at 3 inches is 4.63 cubic yards before waste. For bagged product, The Calculator Site puts a US cubic yard at 13½ two-cubic-foot bags, which turns that same bed into about 63 bags. The identical arithmetic drives the mulch calculator and the topsoil calculator; the stone and gravel tonnage calculator takes the extra step of converting cubic yards to tons, because most yards sell aggregate by weight at a density that varies with the stone.
Sod is where a takeoff most often goes wrong, because pallet coverage is a supplier fact rather than a constant. Easy Takeoffs’ reference uses 450, 500, or 600 sq ft per pallet. Sod Solutions, a grower, puts the real span at 400–700 sq ft: southern slab pallets (16 × 24 in pieces, 2.66 sq ft each) sell as 400, 450, and 500 sq ft; northern mini hand rolls (40 × 18 in, 5 sq ft a piece) come the same way; large rolls (60 × 24 or 80 × 18 in, 10 sq ft each) are packed 500, 600, or 700. The sheet ships a 500 sq ft default because it sits inside both ranges — overwrite it with your grower’s number and the pallet count re-rounds. The sod calculator runs the same conversion interactively.
Pavers produce two quantities from one footprint: the aggregate base and the
bedding layer. Bedding is the settled part — the CMHA (ICPI) guide spec for
pavers on an aggregate base directs that bedding sand be screeded to a nominal 1
in. (25 mm) thickness. Base depth is not settled, and should not be: that same
guide spec carries no base-thickness figure at all — the aggregate base is a
separate section a licensed design professional edits for the project — so what a
takeoff carries is an assumption, not a specification. Easy Takeoffs’ takeoff
reference uses the common 4–6 in range and puts an 800 sq ft patio at 10–15 cubic
yards of base, which is where this sheet’s editable 5 in default lands.
Change the depth — the Depth (in) cell on a paver row in the preview above, or
PAVER_BASE_DEPTH_IN on the workbook’s Conversions tab — to whatever your plan or
engineer specifies, and the cubic yards follow. A paver row takes no waste
factor: base and bedding are volumes under the patio, while the cut waste a
pattern forces falls on the paver units, which this sheet does not count. Size
those in the
paver patio calculator. A block
wall holding the same terrace counts courses, caps and backfill instead, which
is what the
retaining wall block calculator
returns, and the whole hardscape assembly is priced as a job in
what to charge to build a paver patio.
Plants pass straight through as a count — work out the count first with the plant spacing calculator if you are filling an area rather than placing specimens. Edging is linear feet plus waste. Discrete order units — bags, pallets, rolls, plants — always round up, because you cannot buy four tenths of a pallet.
Running the takeoff
- Measure first. Areas, lengths, counts, by zone. Irregular lawns are quicker to break into rectangles and triangles with the lawn area calculator than to guess at.
- One row per zone per material. Front bed mulch and back bed mulch are two rows, not one — you want to be able to check a zone later without re-deriving the whole order.
- Set depth deliberately. Mulch depth and base depth are decisions, not measurements; they drive the volume more than anything else on the row.
- Set waste per material. The shipped percentages are starting points to replace with what your own jobs consume. They drive bulk, sod, and edging rows; a paver row carries no waste factor.
- Read the order summary, then confirm coverage with the supplier before you place the order. Coverage rates are standard estimates, not guarantees.
Where takeoffs go wrong
Four failure modes account for most short orders: treating a supplier’s coverage figure as a universal constant; forgetting that a cut-heavy pattern or a curved bed line consumes more than a rectangle; ordering off a plan revision the site has already moved past; and quietly pricing inside the takeoff, which buries a material shortfall inside a margin conversation where nobody will find it.
Confirm actual coverage, depth, and waste with your supplier before you place the order, and keep the priced version of the job on the estimate — not here.
Frequently asked questions
What is the difference between a landscape takeoff and a landscape estimate?
How do I convert bed square footage into cubic yards of mulch?
How many square feet does a pallet of sod cover?
How much waste should I add to a takeoff?
Can I run the takeoff off a plan set instead of a measured site?
Sources
- Landscaping Takeoffs — material quantity method. Easy Takeoffs. Retrieved .
- Mulch Calculator (area × depth ÷ 324; 13.5 bags per cu yd). The Calculator Site. Retrieved .
- How Many Square Feet Are in a Pallet of Sod?. Sod Solutions. Retrieved .
- Guide Spec PAV-GSP-011-21: Pavers on Aggregate Base (§3.04 — bedding sand screeded to a nominal 1 in.). Concrete Masonry & Hardscapes Association (ICPI + NCMA). Retrieved .