Production Rate Job Time Estimator

Estimate total crew man-hours and on-site time for a multi-task lawn or landscape job from measured quantities, production rates, and a site-difficulty factor. No login, no pricing engine.

Tasks
Difficulty

Quantity: measured area or length for this task — measure first with the Lawn Area Calculator.

Rate: production rate (units/hour). Defaults are typical baselines — verify on a known property before bidding.

Difficulty: slopes, tight corners, obstructions, and wet turf slow you down — bump the difficulty.

Crew and setup

On-site time = total man-hours ÷ crew.

Optional: fixed load/drive/setup minutes added once per job.

Adjust difficulty factors

Defaults interpolate SiteRecon's cited 20–30% easy-vs-difficult production variance. Edit them for steep or obstacle-heavy regions.

Total job man-hours

Add a task to see total man-hours and on-site time.

Total man-hours

On-site duration

Per-task man-hours

TaskQuantityBaseDifficultyMan-hours
Export

man-hours = Σ (quantity ÷ rate × difficulty) + setup; on-site = man-hours ÷ crew How?

How this is calculated

Each task's base hours is its measured quantity divided by its production rate, in matching units per hour. A difficulty factor (Easy 1.00, Moderate 1.15, Difficult 1.25 by default) scales that for the site. Adjusted hours are summed across all tasks, an optional fixed setup term is added once, and the job total is divided by crew size for the advisory on-site duration.

per task:
  baseHours      = quantity / rate          (quantity & rate share a unit)
  difficulty     = easy 1.00 | moderate 1.15 | difficult 1.25  (editable)
  adjustedHours  = baseHours × difficulty

job rollup:
  setupHours        = setupMinutes / 60
  jobManHours       = Σ adjustedHours + setupHours
  crewDurationHours = jobManHours / crewSize          (crew ≥ 1)

The canonical quantity ÷ rate = hours relationship and the three-tier easy/moderate/difficult model (quantified at a 20–30% production variance) are from SiteRecon's Landscaping Production Rates Guide; the 36-inch walk-behind ≈ 22,500 sq ft/hr default is from SiteRecon's estimate guide. Quantity and rate share one unit per row, so the division is unit-free — no cross-unit conversion is applied, and units may differ freely across rows. This tool outputs time only, never a price or a sequenced route.

Formula: man-hours = Σ (quantity ÷ rate × difficulty) + setup; on-site = man-hours ÷ crew

Sources

  1. Landscaping Production Rates Guide. SiteRecon. Retrieved .
  2. How to Estimate a Landscaping Job — The Complete Guide. SiteRecon. Retrieved .
  3. Production Rate Calculator & Man-Hour Benchmark Report. SynkedUP. Retrieved .

Get early access

Fieldwynn is the field-first app we are building for small crews — simple in the truck, powerful in the back office. It is not out yet; join the early-access list and be first when it launches for your trade.